The project involved removal of existing seating, railings, casework, flooring and ceiling finishes. Seating, railing, casework, chalkboards, acoustical wall panels etc. were removed first. Scaffolding was installed to remove the existing ceiling. Plumbing rough in at the restroom, demolition on the lower level & corridors were concurrent with the upper level. Above ceiling fire protection, electrical and mechanical, drywall and acoustical finishes were performed. Light fixtures, mechanical diffusers, grills and sprinkler system trim out were also completed. Testing, balancing, punch list, final cleaning, final inspections and occupancy permit were completed the last two weeks of July. The building was turned over to the owner August 1, 2014.
Owner: Board of Regents of the University System of Georgia